Building Works are Underway!

You probably can’t see it at the moment, but works for the new building are definitely underway. Here are a few important things that you need to know:

• Construction of a new temporary sports hall will start on October 21st. The temporary sports hall is due to be completed 10th February 2014 and then the old sports hall will be demolished.

• New features such as hi-tech windows will be fitted in the new building in April 2014. This means that the new building will be able to retain heat in the winter and protect us from glare in the summer.

• Fencing around the main building will be erected to ensure our school site remains a safe and pleasant environment.